Saturday, May 15, 2010

Africa's first high-speed train to open ahead of World Cup

The Gautrain, Africa's first high-speed rail line, will launch on June 8 in South Africa three days before the opening match of the 2010 football World Cup, the developers said Friday.
Gautrain arrives at O.R. Tambo International Airport outside of Johannesburg
The Gautrain at OR Tambo International Airport near Johannesburg, South Africa

French construction giant Bouygues said the train's first segment, linking OR Tambo International Airport and the posh Johannesburg suburb of Sandton, will open in time for the June 11 kick-off of Africa's first World Cup.

The segment "will be handed over on June 8, three weeks ahead of our original schedule," said Christian Gazaignes, Bouygues' executive director.

For R100 (13 dollars, 10 euros), World Cup visitors will be able to ride the 15 kilometres from the airport to the Sandton hotel district in less than 15 minutes.

In rush-hour traffic, the same trip takes more than an hour by car.

When finished in mid-2011, the 80-kilometre regional express train will link the capital Pretoria with national economic hub Johannesburg, running at speeds of up to 160 kilometres (99 miles) an hour and enabling commuters to make the trip in 42 minutes.

"It's going to give the country a beautiful image of modernity," said Laurence Leblanc, international director of RATP Dev, a subsidiary of French group RATP, the company awarded a 15-year concession to operate the train.

"The Gautrain isn't specifically a World Cup project. It doesn't serve the stadiums," said Leblanc. "But it's a superb project for South Africa's image. That's why we're knocking ourselves out to get ready."

The Bombela Consortium, an international group that includes Bouygues, Canadian firm Bombardier and two South African companies, began construction on the project in 2006.

The developers say they have "worked like crazy" to finish the first section before the World Cup, making up time lost to strikes and construction delays.

The 3.2-million-dollar Gautrain is the first high-speed rail line in Africa. The north African cities of Casablanca, Algiers and Cairo all have metro lines, but none runs as fast or as far as the Gautrain.

South African transportation officials say the train will form the backbone of a new public transport network that will help take traffic off the notoriously congested roads of the greater metropolitan area.

"We're targeting people who have the means to own a small car but would prefer to avoid traffic jams," said Leblanc.

RATP says it is targeting South Africans with a monthly income of 1,030 to 2,580 dollars (about R7000 to R20 000), and predicts 16,000 passengers a day will use the new rail line.

To get them to the train, the company plans to roll out a network of shuttle buses serving the population centres around the train stations.

RATP has set the price for the airport-Sandton route relatively high at 13 dollars (R100). But the Sandton-Pretoria segment will cost just 4.5 dollars (about R30), rivalling the price of the mini-buses that currently provide most of area's mass transit.

Officials hope the price scheme will help turn South Africans onto public transport, in a country where mass transit systems languished for decades under apartheid policies designed to keep whites and blacks apart.

RATP also promises tight security on the trains, using closed-circuit TV cameras, 400 security guards and 50 police officers to convince South Africans to abandon the protective shell of their vehicles.

Sapa-AFP

Sunday, August 30, 2009

Gautrain 2010 decision to be made in October – Van der Merwe

On Tuesday it was still unclear whether the R25,4-billion Gautrain rapid-rail project would be completed in time for the 2010 FIFA World Cup.

Gautrain Management Agency (GMA) CEO Jack van der Merwe said the Bombela consortium, responsible for the project's construction, had indicated that it might be technically feasible to complete the project in time for the June 11 kick-off, but that this was not a certainty.

The project's phase one – the link between the OR Tambo International Airport (ORTIA) and Sandton – was not contractually scheduled to be completed until the end of June.

However, government had previously indicated the need to complete the project in time for the global sports event.

Van der Merwe said it seems as if Bombela would be able to tell GMA in mid-October whether it would be able to wrap up phase one in May.

“So, by the middle of October we will know whether we must pay extra to have the link completed. Then we will also have to decide whether it is worth the money and, if so, where we will find the money.”

Van der Merwe told Parliament's portfolio committee on transport earlier in the day that GMA would not pay an “unreasonable amount” to the Bombela consortium to accelerate the project for a four-week-long event.

“It was never said that this was a soccer project. This train has to run for another 100 years. You cannot spend this kind of money on a four-week event,” news agency Sapa quoted Van der Merwe as saying.

The Gautrain project was announced in January 2000. South Africa was awarded the World Cup in April 2004.

Van der Merwe said 125 buses would be ready to transport passengers from the airport to their hotels should the train not be ready in time.

Phase two of the Gautrain project was scheduled for completion in March 2011, ultimately linking Johannesburg, Tshwane and ORTIA.

via

Tuesday, August 25, 2009

2010: Gautrain may not be ready

Cape Town - The R25bn Gautrain project may not be ready in time for the 2010 Soccer World Cup, the project's chief executive told Parliament on Tuesday.

Jack Van der Merwe told Parliament's portfolio committee on transport that the Gautrain Management Agency (GMA) would not pay an "unreasonable amount" to the Bombela consortium to accelerate the project for a four-week-long event.

"There has to be value for money. If we have to pay an unreasonable amount, the answer is no," Van der Merwe said.

"It was never said that this was a soccer project. This train has to run for another 100 years.

"You cannot spend this kind of money on a four week event."

The World Cup is due to run from June 11 to July 11.

Costs


The Gautrain project was announced in January 2000. South Africa was awarded the World Cup in April 2004.

Van der Merwe did not know how much it would cost to accelerate the construction work to May 27.

The GMA was negotiating with Bombela.

He said any extra costs would have to be paid by the provincial or national government.

The costs would not be passed on to passengers through increased ticket fares, which are expected to cost between 50 and 60 cents a kilometre or R20 for a trip from Johannesburg to Pretoria.

Van der Merwe said 125 buses would be ready to transport passengers from the airport to their hotels should the train - which will run from the airport to central Johannesburg and Pretoria - not be ready in time.

'Carrot' for motorists


Van der Merwe said the Gautrain would be "carrot" for motorists using the Ben Schoeman highway between Johannesburg and Pretoria.

The train journey between central Johannesburg and Hatfield in Pretoria will take approximately 38 minutes and will cost commuters between R800 and R1 000 a month.

Traffic congestion and a R1 000 a month toll fee to be introduced on the highway would be the "stick".

"People will be stuck in traffic on the Ben Schoeman and they will see a train shoot past and they'll think maybe I made a mistake.

"Then five minutes later they'll see another train and they'll think I really did make a mistake."